The building, formally known as 22 Arlington Street, situated next to Green Park, is being dismantled to make way for further development.
Client: Confidential
Project Value: Confidential
Date of Completion: 2021
The existing building is a separate nine storey (basement, ground, six storeys of office and plant level) 1970s office building, with one level of basement, and open courtyard areas to the east and west sides.
The dismantling of the existing building has a programme to progress deconstruction through to the end of 2021. The mitigation and management of disruption to the local environment, nearby properties, including local residents, is a priority, including noise, vibration and dust suppression. Toureen are utilising the latest machinery and techniques to ensure any impact on the local area and neighbouring properties/uses is kept to a minimum.